Observatory progress – Phases 2, 3 and 4

Posted by @ 8:18 pm on Friday 1st May, 2009.

Readers may remember that Nick and I constructed a prototype telescope pier way back in December. If you want to see what it looked like at the time, the post is here.

Well, that was Phase 1, and since then there have been developments...

Phase 2 (the move from prototype to working sample):

First up, preliminary tests indicated that the dimensions were OK but the ad-hoc angle-iron mountings were inadequate. We knew that they would have to be replaced, as they were only used as a temporary measure in order to allow flexure, resonance and vibration-damping testing. As you can see, they've been replaced with something a bit more substantial.

Second, a large hole was drilled in the side to allow sand-filling to dampen any excessive vibes. We also put a few M6 tapped holes in the side to allow for any future need for attaching brackets, gadgets, earth-tags and other such things.

Third, the whole shebang (apart from the threads) was phosphated and powdercoated which looks neat and should preserve the thing for quite a few years.

Phase 3 (the installation of the pier) was completed a week ago. After the ball-aching job of making a deep and heavy concrete base (see here) the pier was nutted onto the set-in studding, and a base of old slabs was put down around it to support the bearers.

Phase 4 is now complete - the construction of a sound raised floor-frame. To replace the somewhat inadequate floor that (eventually) came with the new shed, I made a frame of 4x2s which has been given several liberal coats of preservative. This frame sits on bearers (some old 3x3 fence-posts) which should last a few years before they rot. These bearers are not fixed, so they can be replaced one at a time if necessary - they cost nowt when "acquired" from the local tip.

Here are a few snapshots of the project so far:

The revised mounting-plate nutted to the studding in concrete base

The slabs have it surrounded!

The floor-frame supported by bearers (old fence-posts)

Phase 5 will be interesting - it's the bit where we assemble the shed walls. Now, if only I had a full set...

Have your say - submit a comment

THE SMALL(ish) PRINT... (updated 23/07/2016)

By submitting a comment to this blog you grant me permission to reproduce its content and to reproduce the submitted name/URL in attribution. I will leave your content in its intended place and in its unedited form unless one or more of the following apply:

If you ask me to modify, move or delete your content, I’ll consider making the requested change(s) so long as there’s no significant alteration of the context of the content or of any debate associated with it;
If you change your email address or URL, I’ll update these details in older comments so that I'm not displaying dead links;
If I decide to change the theme or layout of this blog, thus affecting the placement and/or visibility of comments, I’ll make whatever changes I see fit for the smooth running of this blog;
If any comment contains insulting profanity or other content which I deem to be causing or likely to cause trouble, I’ll edit or delete as I see fit for the smooth running of this blog. I’ll try to remember to display the reason(s) for whatever editing I do, so that folk aren’t left hanging wondering what happened and why. If you can at least try to "disguise" your swearing, it would be much appreciated.

Other things to consider:

Comments must contain at least 3 characters;
You can use some code in comments, feel free to give it a shot and see what works;
If adding pics, the recommended maximum dimension is 600px.;
Comments containing many links will be held for moderation;
I reserve the right to amend this policy in line with proven applicable current legislation;
Free Speech: you may well have the right to it, but you've no right to compel me to a) listen to it, or b) publish it!